YVR Parkade

Vancouver, British Columbia

Eagle Builders was chosen for this project based on our production capacity and product quality, which utilized superior steel forms. The project involved a six-level parkade structure with 525 railcars of precast transported from Red Deer to New Westminster, B.C. Eagle developed a rail logistics plan, installed two 20T overhead cranes, and implemented impact testing and securement designs for safe transport. The project achieved an average of over 18 pieces erected daily, with a maximum of 30 pieces in a 10-hour day. The exterior spandrel panels used an architectural formliner.

Project Stats

  • 2190 Precast Panels
  • 13,000 Total m³ Concrete
  • 178,000 sq ft
  • 855,000 Usable sq ft
  • 200 Days to Produce
  • 118 Days to Erect Shell

© 2024 Eagle Builders | Log in | Privacy Policy | Website by EDGE Marketing & Design Inc.