BRID Canal Bridge

Taber, Alberta

The Bow River Irrigation District Canal Bridge was constructed to meet rigorous timeline requirements in 2021. Despite a challenging installation process, Eagle Builders was able to convert the five span bridge to a three span bridge with no topping required.

Project Stats

  • 3 days to install
  • 24 girders
  • 8 days precast production
  • 4145 sq ft
  • SL510 type bridge
  • 148 m³ of concrete used
  • 14 and 12 meter long girders